The project will be divided in two one-year periods, finishing at two major milesones (M at +12, and F at +24). For the sake of internal synchronization, two intermediary milestones will take place (IM1 at +6 and IM2 at +18).
+------+------+------+------+------+------+------+------+
Month 0 3 6 9 12 15 18 21 24
+------+------+------+------+------+------+------+------+
Period | I | II |
+------+------+------+------+------+------+------+------+
Milest. | IM1 M IM2 F
+------+------+------+------+------+------+------+------+
WP1 RESOURCE BUILDING | | |
|>>>> T1.1 >>>| | | |
|>>>> T1.2 >>>|>>>>>>>>>>>>>| | |
+------+------+------+------+------+------+------+------+
WP2 TOOL APPLICATION TO CORPUS | | |
|>>>> T2.1 >>>|>>>>>>>>>>>>>| | |
| |>>>> T2.2 >>>|>>>>>>>>>>>>>| |
| | |>>>> T2.3 >>>|>>>>>>>>>>>>>|
+------+------+------+------+------+------+------+------+
Meetgs KCM MPM EPM
+------+------+------+------+------+------+------+------+
Abbreviations:
IM1 = Intermediary milestone 1
IM2 = Intermediary milestone 2
KOM = Kick-off meeting
MPM = Mid-project meeting
EPM = End-of-project meeting