The project will be divided in two one-year periods, finishing at two major milesones (M at +12, and F at +24). For the sake of internal synchronization, two intermediary milestones will take place (IM1 at +6 and IM2 at +18).
+------+------+------+------+------+------+------+------+ Month 0 3 6 9 12 15 18 21 24 +------+------+------+------+------+------+------+------+ Period | I | II | +------+------+------+------+------+------+------+------+ Milest. | IM1 M IM2 F +------+------+------+------+------+------+------+------+ WP1 RESOURCE BUILDING | | | |>>>> T1.1 >>>| | | | |>>>> T1.2 >>>|>>>>>>>>>>>>>| | | +------+------+------+------+------+------+------+------+ WP2 TOOL APPLICATION TO CORPUS | | | |>>>> T2.1 >>>|>>>>>>>>>>>>>| | | | |>>>> T2.2 >>>|>>>>>>>>>>>>>| | | | |>>>> T2.3 >>>|>>>>>>>>>>>>>| +------+------+------+------+------+------+------+------+ Meetgs KCM MPM EPM +------+------+------+------+------+------+------+------+ Abbreviations: IM1 = Intermediary milestone 1 IM2 = Intermediary milestone 2 KOM = Kick-off meeting MPM = Mid-project meeting EPM = End-of-project meeting